Thompson Peak Parkway Bridge in DC Ranch: What the Project Changes

October 29, 2026

"Currently, the four lanes of traffic that travel Thompson Peak Parkway merge into two travel lanes over the existing bridge." That sentence comes from a City of Scottsdale staff report quoted by the Scottsdale Progress ahead of the September 22 City Council meeting. Anyone who drives the parkway through DC Ranch knows where this happens. The road narrows over the Reata Wash, between E. Desert Camp Drive and E. Windgate Pass Drive, and then widens again.

On Monday, Nov. 2, the city started building the second bridge that ends that narrowing. The narrowing is the missing half of a design that has existed since DC Ranch was laid out, and most of the remaining decisions are about making the new half look like the old one.

Designed for two crossings, built with one

The city's project page tells the story plainly. When DC Ranch was built, the city and the developer agreed that the developer would design the Thompson Peak Parkway bridges over the Reata Wash but would build only one of them, because the new community did not yet have enough traffic to need both. The second bridge was left on paper until traffic justified it, and the city took on the job of building it when that happened.

The single bridge has handled the cars well enough. According to the city, the problem is bicycles. More people now ride this stretch, and the city calls the bridge "a safety concern for motorists and cyclists." Today, four car lanes and two bike lanes squeeze into two car lanes and two bike lanes over the wash. That squeeze is the narrowing every driver and rider passes through.

That history explains why the new bridge looks the way it does on paper. In August 2025, the city's Paths and Trails Subcommittee reviewed a design whose "configuration and aesthetics will match the existing eastbound bridge." The new structure will not be identical to the first, but it is designed to carry the same lane layout and the same look.

How DC Ranch got it onto the ballot

Unbuilt halves of plans can wait a long time. This one got moving because, according to DC Ranch's own project page, the community pushed for it, and the bridge expansion became the only transportation project in Scottsdale's 2019 bond election. The city lists it as Project 62 under Question 2, Community Spaces and Infrastructure, worded on the ballot as a bridge over Reata Pass Wash "to Improve Safety."

That election was large. In November 2019, Scottsdale voters approved three bond questions totaling $319 million for 58 projects, and the Scottsdale Progress reported that 26 of them are listed as completed. The bridge was one of the projects still waiting.

The cost also changed along the way. Here are the figures in order:

  • $6.3 million, the amount for this bridge in the 2019 package voters approved
  • $8,085,461.26, the most the city can pay Ames Construction, Inc. under the construction contract, Contract No. 27IBF097, authorized by Resolution No. 13778
  • $14.2 million, the total project budget on the city's project page, paid for by 2019 bonds and the city's 0.2% transportation sales tax

The Scottsdale Progress said project No. 62 "appears to be barreling far north of the original estimate," as many earlier bond projects did. Even so, the contract passed without debate. The City Council's marked agenda for September 22, 2026 records the award as approved on consent. Kimley-Horn designed the bridge.

The first phase happens down in the wash

Drivers will see very little at first, and the reason is that the early work happens below the road. The city's project page describes the opening phase this way:

  1. Native plant salvage and relocation. Desert plants in the work area are removed and kept in a temporary nursery on site.
  2. Underground utility work. Crews find buried lines and move them if needed.
  3. Shaft drilling for the bridge supports, most of it below road level in the Reata Wash.

Work runs Monday through Friday, 7 a.m. to 5 p.m. The contractor's staging area is on site, and the city says travel lanes will not be affected during this phase. The city has not yet posted a traffic plan for the phases after this one. Until it does, any prediction about lane closures is a guess.

For now, the most visible change will probably be the desert itself. The salvage step means the plants along the wash are being dug up and stored nearby, not cleared away.

The fight over matching the first bridge

A matching look depends on matching materials, and that is where DC Ranch's Community Council focused. In July 2026, the city shared its initial designs with the Community Council, and according to DC Ranch, the board responded on four points:

  • Fake stone is not acceptable, the stone should match the original bridge by use of DC Cobble
  • Jersey barriers along the entire length of the bridge are also unacceptable, suggest removing the sidewalk and continuing the natural path through the wash
  • While deleting the arched supports under the bridge is not preferred, the cost savings it allows the city is understandable
  • Metal railings instead of wood are acceptable as long as the design matches the original bridge; the original bridge railings should also be replaced with metal as part of the project as they are in poor condition

Read as a design brief, the feedback is careful. The board held firm on stone, because DC Cobble is part of how DC Ranch looks. It accepted losing the arched supports because the city could save money. It accepted metal railings as long as they match, and asked the city to put the same metal railings on the original bridge, so the two spans end up matching each other. The railing request reaches back and updates the bridge already standing there.

The barrier comment points to a real tension in the plan. The 2025 design included a five-foot sidewalk with a barrier between it and traffic. The Community Council suggested a natural path through the wash below instead. Both are meant to serve people on foot. One puts them on the bridge and the other puts them in the wash.

The city held a public open house on the design and construction timeline on September 9 at The Homestead. The final design choices on stone and barriers will become clear as the bridge goes up, and the stone facing will be visible from the parkway.

The bridge will also come with art. Under city ordinance, the project has to include a public art piece.

How traffic splits when it's done

When both spans are finished, each will carry one direction. The new bridge will take westbound traffic with two 12-foot lanes, a five-foot bike lane and a five-foot sidewalk, and the existing bridge will carry eastbound traffic only. The 2025 design review also planned a noise study to decide whether a noise wall or other noise control is needed.

The finished result reaches well past the wash. According to the city, the new bridge will give Thompson Peak Parkway four continuous lanes with bike lanes from Scottsdale Road to 100th Street, and the city expects better access to nearby parks and schools. The bridge is the one gap left in that stretch.

The finish date depends on which source you read. The city says construction will take about 12 months from the November 2 start, which points to late 2027. DC Ranch wrote in July 2025 that it had worked with the city to move completion up from 2028 to spring 2027. The city's page was updated more recently, on October 16, 2026. For the 7 a.m. drive or the Saturday ride over the wash, a year of construction is the safer assumption.

The stone facing and the railings will be the parts of this project you see every day from the parkway. If you live near the parkway and have been wondering how a project like this, built well or poorly, affects the streetscape around your home, I would be glad to walk through it with you. Sarah Scannell is happy to begin a conversation.